House and Garage Demolition in Cupertino, CA: Permit Checklist and Fees
- Cupertino requires a demolition permit for any building, structure or pool. The city's sample site plan marks a tool shed and a garage for demolition.
- The checklist asks for a PG&E letter confirming gas and electric were terminated at the main/street, a BAAQMD letter with an ASB number, a pest control letter and a PCB screening form.
- Every residential demolition needs a debris management plan through Green Halo.
- City fee for a home (R-3) up to 3,000 sq ft: $880, plus $306 for each additional 3,000 sq ft (effective July 1, 2026). The city lists 10 days for review.
Cupertino demolition permit at a glance
| Question | What the City of Cupertino says |
|---|---|
| Is a permit required? | "Demolition permits are required for all sites where a demolition of any building, structure, and/or pool is proposed." |
| How to apply | Complete a Demolition Permit Application (D). It can be submitted together with the building permit for the new home, but the new building permit is not issued until the demolition permit is. |
| Fees | Due when you submit. Residential (R-3) up to 3,000 sq ft: $880; each additional 3,000 sq ft: $306; residential pool: $589 (Resolution 26-047, effective July 1, 2026). |
| Review time | The city lists 10 days for the initial review and 10 days for resubmittals. |
| Site plan | One scaled digital copy showing garages, carports, sheds and pools, and every on-site tree with species and diameter at 4.5 ft above grade. |
| PG&E | A termination letter confirming gas and electric were terminated at the main/street. The checklist says to call PG&E at 408-725-3325 to schedule the disconnect. |
| Air district | A BAAQMD notification letter with an ASB number (BAAQMD calls it the job number, or J number). |
| Pests | A letter from a pest control contractor stating the site was inspected and is clear of pests. |
| PCB form | A PCB Screening Assessment Form. |
| Debris | A Construction and Demolition Debris Management Plan through Green Halo for every residential demolition. |
| Historic check | Verify whether the building is a historic landmark and get clearance from Planning (planning@cupertino.gov). |
| Trees | Tree protection is inspected by Public Works (408-777-3354) before the permit is issued. |
Source: City of Cupertino: Procedure Checklist for Demolition Permits (PDF, rev. 1/9/26) (opens the official site) · City of Cupertino: Building Fee Schedule (PDF, effective July 1, 2026) (opens the official site) · City of Cupertino: Permits (permit timelines) (opens the official site)
How a Cupertino demolition usually runs
- Visit and written price. We check the structures, access, trees and utilities.
- PG&E and BAAQMD first. We start both right away. BAAQMD needs notice at least 10 working days before any demolition.
- Pest letter and PCB form. Both go in the package.
- Tree protection. Installed and inspected by Public Works before the permit is issued.
- Application and fees. Application D, site plan and the Green Halo debris plan, with fees paid at submittal.
- Demolition, recycling and final. We stay until the city closes the permit.
Review and utility times depend on the city and PG&E, so we confirm the start date once the permit is issued.
Source: City of Cupertino: Procedure Checklist for Demolition Permits (PDF, rev. 1/9/26) (opens the official site) · BAAQMD: Asbestos Demolition and Renovation Notification (opens the official site)
Garages, sheds and pools in Cupertino
Cupertino does not list a size exemption: its sample site plan shows a tool shed and a garage marked for demolition, and pools need a permit too ($589, plus a Cupertino Sewer District permit to drain). See our Cupertino pool removal guide and garage and shed demolition.
Source: City of Cupertino: Procedure Checklist for Demolition Permits (PDF, rev. 1/9/26) (opens the official site) · City of Cupertino: Building Fee Schedule (PDF, effective July 1, 2026) (opens the official site)
Demolition in Cupertino: common questions
How much is a demolition permit in Cupertino?
For a home (R-3) up to 3,000 sq ft the city fee is $880, plus $306 for each additional 3,000 sq ft, in the fee schedule effective July 1, 2026. Fees are due at submittal.
Do I need a permit to tear down a shed in Cupertino?
Yes. Cupertino requires a demolition permit for any building, structure or pool, and its sample site plan includes a tool shed.
What is the ASB number for a Cupertino demolition?
It is the number on the BAAQMD notification letter (BAAQMD calls it the job number or J number). Cupertino asks for that letter with the demolition permit.
How long does Cupertino take to review a demolition permit?
The city lists 10 days for the initial review and 10 days for each resubmittal.
Keep reading
- Demolition permits in the Bay Area, step by step
- PG&E disconnect before demolition
- Demolition permit in Pleasanton
- Pool removal in Cupertino
- Bay Demo house demolition service
Official sources
- City of Cupertino: Procedure Checklist for Demolition Permits (PDF, rev. 1/9/26) (opens the official site)
- City of Cupertino: Building Fee Schedule (PDF, effective July 1, 2026) (opens the official site)
- City of Cupertino: Permits (permit timelines) (opens the official site)
- BAAQMD: Asbestos Demolition and Renovation Notification (opens the official site)