House and Garage Demolition in Pleasanton, CA: The Permit, Step by Step
- Pleasanton requires a demolition permit for the complete or partial removal of any building or structure. The handout lists no size exemption, so sheds and garages are included.
- Check with the Planning Division first, then apply online through the Accela Citizen Portal.
- The application needs the BAAQMD clearance, a PG&E letter confirming gas and electric are disconnected, a PCB screening form, a letter from the demolition contractor, and dust control and truck route plans.
- Projects valued at $25,000 or more need a Waste Management Plan ($150) approved before any inspection can be scheduled.
Pleasanton demolition permit at a glance
| Question | What the City of Pleasanton says |
|---|---|
| Is a permit required? | "A demolition permit is required for the complete or partial removal of any building or structure." |
| Before you apply | Contact the Planning Division ((925) 437-4009, pod@cityofpleasantonca.gov) to confirm planning rules and get any planning approval. |
| Where to apply | Online through the Accela Citizen Portal (ACA): application, plans and documents. |
| Review time | The handout says first-round review typically takes about three weeks. |
| Air district | A copy of the BAAQMD clearance, or BAAQMD documentation that clearance is not required. |
| Utilities | A PG&E letter showing gas and electric have been disconnected. Call Construction Services Inspection at (925) 931-5650 when sewer or water laterals are exposed at the property line. |
| PCB form | A completed PCBs Screening Assessment Form, one per building being demolished. |
| Contractor letter | Timeline, work hours, dust and noise control, demolition method and site security. |
| Plans | Site plan (parcel number, acreage, building square footage, wells, septic, utilities, meters), demolition plan with every utility to be removed, dust control plan and truck route plan. |
| Debris | Waste Management Plan through Green Halo for projects valued at $25,000 or more, approved before any inspection is scheduled. Fee: $150. |
| Deposits and other clearances | Cash bonds may be required for erosion control, hazard mitigation or tree protection. Fire Department clearance if required. Encroachment permit and traffic control plan for work in the public right-of-way. |
| Fees | Permit fees are based on valuation, plus a 5% technology fee. Plan review is 75% (or 100%, per the fee schedule) of permit fees and surcharges, $180 minimum (fee schedule January 1, 2026). |
Source: City of Pleasanton: Demolition Permit Submittal Requirements (PDF, rev. 01.26) (opens the official site) · City of Pleasanton: Building Permit and Plan Review Fees (PDF, January 1, 2026) (opens the official site)
How a Pleasanton demolition usually runs
- Visit and written price. We walk the site, check access, utilities and anything that needs testing.
- Planning check. Confirm with the Planning Division that the demolition fits the zoning and whether any approval is needed.
- PG&E and BAAQMD. Request the gas and electric disconnect early, and file the BAAQMD notification (every demolition needs one, at least 10 working days before work starts).
- Application. Upload the site plan, demolition plan, contractor letter, PCB form, dust and truck route plans in Accela.
- Waste plan. For projects of $25,000 or more, the Green Halo plan must be approved before the first inspection.
- Demolition, recycling and final. Debris goes to recycling facilities and we stay until the city closes the permit.
How long the city and PG&E take depends on their workload, so we confirm the start date once the permit is issued.
Source: City of Pleasanton: Demolition Permit Submittal Requirements (PDF, rev. 01.26) (opens the official site) · BAAQMD: Asbestos Demolition and Renovation Notification (opens the official site)
Garages and sheds in Pleasanton
Some cities exempt small sheds. Pleasanton's handout does not: the permit covers the removal of any building or structure. If you are clearing a garage or a shed for an ADU, plan the demolition permit and the ADU application together. See our garage and shed demolition service.
Demolition in Pleasanton: common questions
Do I need a permit to demolish a shed in Pleasanton?
Yes. Pleasanton requires a demolition permit for the complete or partial removal of any building or structure, and its handout lists no size exemption.
How long does Pleasanton take to review a demolition permit?
The city handout says first-round review typically takes about three weeks.
Does Pleasanton require a recycling plan for demolition?
Yes, for demolition projects valued at $25,000 or more: a Waste Management Plan through Green Halo, approved before any inspection. The city fee is $150.
What do I need from PG&E to demolish in Pleasanton?
A PG&E letter showing that gas and electric utilities have been disconnected, included with the permit application.
Keep reading
- Demolition permits in the Bay Area, step by step
- PG&E disconnect before demolition
- Demolition permit in Cupertino
- Pool removal in Pleasanton
- Bay Demo house demolition service
Official sources
- City of Pleasanton: Demolition Permit Submittal Requirements (PDF, rev. 01.26) (opens the official site)
- City of Pleasanton: Building Permit and Plan Review Fees (PDF, January 1, 2026) (opens the official site)
- BAAQMD: Asbestos Demolition and Renovation Notification (opens the official site)