- In most Bay Area cities you need a permit to fill in or remove an inground pool, and the city inspects the work.
- Pleasanton and Cupertino offer two paths: leave the shell (landscaping only) or full removal with an engineer's compaction report (buildable).
- Each city sets its own documents, inspections and fee. Pleasanton and Cupertino publish theirs below.
Pool removal permit rules by city
| City or area | How to apply | Engineer's report | Worth knowing |
|---|---|---|---|
| Pleasanton | Online (ACA). Can qualify for over-the-counter review. | Full removal only (90% compaction report). | About 1 week for first review. Pool Demolition Requirements (PDF) (opens the official site) |
| Cupertino | Online (Accela Citizen Access). | Option B (buildable) only. | City fee $589 (July 2026). Swimming Pool Removal Requirements (PDF) (opens the official site) |
Not on the list? Your city still sets its own rules. Call the building department or ask us. We check this table every 90 days; last check Nov 17, 2026.
Partial fill-in or full removal: what the permit changes
A partial removal (abandoning the pool in place) breaks openings in the floor and fills the shell; some cities also ask for the top of the walls to come out. A full removal takes the whole shell out. In the cities we have checked, the partial path skips the compaction test but leaves the area for landscaping, while a full removal with an engineer's compaction report keeps it buildable. Decide what you want to build before you choose the method.
What Pleasanton and Cupertino ask for
- A site plan with the pool that says which option you chose.
- Gas and electrical for the pool shut off: Pleasanton spells out the capping, Cupertino verifies them as terminated.
- Pool water drained the approved way: to the sanitary sewer in Pleasanton, with a Sewer District permit in Cupertino.
- A final inspection to close the permit, plus an earlier one in Pleasanton and for Cupertino Option A.
What it costs, and which method to choose
Our recent written estimates run $10,500 to $11,500 for a partial removal and $18,000 to $21,500 for a full removal, permit included. See the pool removal cost breakdown (with a quick price check) and partial vs full pool removal to choose a method before you apply.
Pool removal permit terms, in plain words
- Abandonment (partial removal, fill-in): the shell stays in the ground, holes are broken in the floor and the pool is filled. Pleasanton calls it Option 1, Cupertino Option A.
- Full removal: the whole shell comes out. Pleasanton Option 2, Cupertino Option B.
- Bond beam: the thick concrete ring at the top of the pool wall, under the coping. Pleasanton requires it removed all around in a partial removal.
- Engineered fill: soil placed in compacted layers and tested by a geotechnical or civil engineer.
- 90% compaction (ASTM D1557): the density Pleasanton requires for the fill in a full removal.
- Compaction report: the engineer's signed report handed to the inspector at the final. It is what makes the area buildable.
- Over the counter (OTC): plan review done at the counter by appointment instead of a full plan check. Pleasanton lists residential pool demolition as eligible.
- Final inspection: the last city inspection that closes the permit. Keep the record for when you sell.
Your city is not on the list?
We add a city only after reading its official pool removal rules. Until then, call your building department or ask us: we pull pool removal permits across the Bay Area and know what each department expects.
Selling a home with a filled-in pool
Keep the closed permit and the final inspection record. A permitted removal is easy to disclose to a buyer. An unpermitted fill is what causes trouble at inspection.
Pool removal permit questions
Do I need a permit to remove a pool in the Bay Area?
In most Bay Area cities, yes. Pleasanton and Cupertino, for example, require a permit to fill in or remove a pool and inspect the work. Rules differ by city, so check with your building department.
Can I fill in a pool without a permit?
Not in the cities on this page. Filling in a pool is a permitted, inspected job, and an unpermitted fill can cause problems when you sell.
Do I need an engineer to remove my pool?
In Pleasanton and Cupertino, only if you want the area to be buildable: a full removal with an engineer's compaction report. Leaving the shell in place skips the engineer but limits the area to landscaping. Other cities may differ.
Official sources
- City of Pleasanton: Pool Demolition Requirements (PDF, rev. 01.26) (opens the official site)
- City of Cupertino: Swimming Pool Removal Requirements (PDF, 3/2024) (opens the official site)
- City of Cupertino: Building Fee Schedule (PDF, effective July 1, 2026) (opens the official site)